The school and dormitory is made up of a group of 3 buildings, built between 1969 and 1995.

 

Building 1995 is structurally sound but needed renovating, so the work was started here.  

Building 1995 was lifted 5 feet in 2019, to prevent water entry when the area is flooded.

Then the renovation (steelwork, brickwork, electrical, plumbing, plastering, painting, woodwork, aluminum partitions, and installing a drainage ditch) began.

The renovation work was completed in June 2020!   

 

 

 

             

We have recently learned that it is possible to also lift

and renovate the two older buildings.

To achieve these objectives...........